PROJECT: I-210 III LOGISTICS CENTER
The I-210 III Logistics Center is a prime project for the Earth Basics team. Within the City limits of Rialto this site required over 100,000 cubic yards of excavation and over 70,000 of fill. Pad subgrade was complete and a pad certification came in a timely manner. On time and ready for the next set of contractors!
The equipment used for this site consisted of: (4)- 637 Caterpillar scrapers, (2)- 623 Caterpillar scrapers, (2)- 651 Caterpillar scrapers and support equipment consisting of 4000 gallon water truck 8000 gallons 623 water pool Caterpillar, a (2)-John Deere 772 GP (motorgrader) scraper blade and a D6 Cat Dozer.
IMG_0019
I-210 Logistics Center Project
I-210 Logistics Center Project. Land cleared and ready for the scrapers. Earth Basics.